Hindustan Aeronautics Limited (HAL), a state-run aircraft maker, has told the Indian Air Force (IAF) it will deliver 16 to 18 Tejas Mk-1A fighter jets by March 31, 2027.
Officials familiar with the talks said this on Monday.
The promise came at a high-level review meeting at Air Headquarters last week.
The meeting on November 16 was attended by IAF chief Air Chief Marshal Ashutosh Dixit and HAL chairman Ravi K.
The Tejas is India's own light combat fighter. A fighter squadron usually has around 18 aircraft.
So this batch is a major step for the Air Force.
Key points
- HAL will deliver 16 to 18 Tejas Mk-1A jets by March 31, 2027.
- The IAF will accept them only if they meet full capability requirements.
- The first deliveries are nearly two years behind the original schedule.
- Two contracts cover 180 jets, worth a combined ₹1.1 lakh crore.
Why are these jets so late?
The first order for 83 jets was signed in February 2021.
The first delivery was due in March 2024, but that deadline was missed.
- February 2021First order for 83 jets was signed
- March 2024First delivery was due, but the deadline was missed
- November 16High-level review meeting held at Air Headquarters
- March 31, 2027HAL promised 16 to 18 Tejas Mk-1A jets by this date
Graphic: News Anek, from the facts in this report
One major reason was the late supply of F404-IN20 engines from US firm GE Aerospace.
Certification delays also slowed the work.
What still needs to be cleared before delivery?
Officials said most hardware problems have been solved. This includes issues linked to weapons trials.
Software problems, including those related to the radar, are in their final stages.
HAL must also get approvals from CEMILAC in Bengaluru and DGAQA.
These papers allow the Air Force to operate the aircraft within set limits.
So why does this matter for India?
The IAF has 29 fighter squadrons, against an authorised strength of 42.5.
The Tejas will replace MiG-21 jets, which retired last year after more than six decades of service.
HAL aims to finish the 2021 order in three to four years.
Deliveries under the second contract are expected to begin in 2027-28.
This is an Indian-built fighter.
Its progress affects how strong the Air Force is, and how well the country's defence plans stay on track.
Sources
- Hindustan Times: First batch of delayed LCAs to be delivered by March: HAL to Indian Air Force | India News
- India.com: Big boost for IAF: HAL assures handover of 18 Tejas Mk-1A fighter jets by March 2027, says no compromise on capabilities
- Aviacionline: HAL pledges a Tejas Mk1A squadron to the Indian Air Force by March 2027